Malvas
Developed with the purpose of generating energy for the total sale of energy in the MEM, and to have an equity investment for shareholders.
508.20 kW DC / 375 kW AC
DC/AC Installed Capacity
820.74
Annual Energy Generated

Problem
One of the main problems was the limited availability of critical equipment and materials, putting execution times at risk. To overcome this, accelerated logistics and proactive supply management were implemented, ensuring timely delivery and early connection of the system to the electricity market
Limited availability of critical equipment and materials.
Risk in the project execution times.
Implementation of accelerated logistics and proactive supply management.
Timely delivery and early connection of the system to the electrical market.
Initial Challenges
The main challenge was to accelerate the start-up of the solar system installed on the floor, intended for the total sale of energy in the electricity market. An efficient and coordinated execution strategy was implemented to meet established deadlines, allowing the generation and sale of energy to begin in the shortest possible time, thus optimizing the return on investment.
01
Accelerated start-up
Priority was given to the rapid entry into operation of the solar system installed on the floor.
02
Energy sales model
The system was designed for the total sale of energy in the electricity market.
03
Efficient and coordinated execution
A strategy focused on strictly complying with established deadlines was implemented.
04
Optimizing return on investment
The early start of energy generation and sale made it possible to maximize the project's return.
Project Timeline
Visual summary of the stages of the project, showing the planning, execution and key times for its proper development.
Sep-22
Kick-off
Oct-22
Design and Engineering
Apr-23
Execution & Procedures
Sep-23
Start of operations
.avif)

Solution
Advance logistics management was carried out with multiple suppliers, prioritizing critical components and establishing direct delivery routes to the site, which allowed us to maintain the schedule and connect the system in record time.
.avif)
Key points
01
Running on night and weekend hours to avoid operational interruptions.
02
Staged planning with constant monitoring of progress.
03
Direct communication with plant personnel.
04
Continuous coordination with the industrial safety team.
“We are very satisfied with HHGM. They met a tight schedule and delivered the system ready to operate ahead of schedule, allowing us to start selling energy and see results in a short time.”
Case studies
Results we have achieved for our clients
.avif)

673.56 kW DC/
487.50 kW AC
487.50 kW AC
DC/AC Installed Capacity
“We were impressed by HHGM's ability to work within an active industrial environment without affecting our operations. Their team was organized, punctual and very professional, achieving a clean and safe installation within the established times.”


313.65 kW DC/
240 kW AC
240 kW AC
DC/AC Installed Capacity
“HHGM demonstrated great technical expertise in adapting the solar system to the demanding conditions of our plant. They provided us with practical and safe solutions, always with close attention and impeccable professionalism.”
More case studies
Liberate you potential and request your quote.
A strategic improvement for your entire operation.
Our team analyzes your current infrastructure, identifies hidden inefficiencies and designs a customized solution that reduces energy costs, improves system performance and strengthens long-term operational stability.