Borgwarner Saltillo

The project was developed for a company in the automotive industry, in its new plant, which had a high energy consumption.
538.08  kW DC / 437.50 kW AC
DC/AC Installed Capacity
775
Annual Energy Generated
Problem

The limitation of schedules for carrying out installation work, since the production areas were kept operating continuously. This made it necessary to carefully coordinate access, maneuvers and safety measures such as working at heights and work with electrical hazards, as well as carrying out part of the tasks so as not to interfere with the production line, coordinating with CFE.

Limited hours due to the continuous operation of production areas.
Coordination of accesses and maneuvers so as not to interfere with the production line.
Reinforced safety measures, including work at height and electrical hazards.
Coordinated execution with CFE to carry out the tasks without affecting the operation.

Initial Challenges

Technical and logistical coordination within the automotive company's facilities, where it was necessary to carefully plan the installation of the panels between the company and the CFE. In addition, the structural and electrical design of the new plant was reviewed to ensure the compatibility of the solar system with the new infrastructure, ensuring an orderly and safe development of the project.

01

Technical and logistic coordination

Detailed planning of the installation within the automotive company's facilities, in coordination with the company and CFE.

02

Joint installation planning

Alignment between the parties involved to define times, accesses and working conditions.

03

Structural review of the project

Evaluation of the structural design of the new plant to ensure the correct integration of the solar system.

04

Electrical compatibility and safety

Verification of the electrical system to ensure an orderly, safe and compatible development with the new infrastructure.

Project Timeline

Visual summary of the stages of the project, showing the planning, execution and key times for its proper development.
Aug-24
Kick-off
Sep-24
Design and Engineering
Jan-25
Execution & Procedures
Mar-25
Start of operations
Solution
A work plan was drawn up in stages, carrying out critical maneuvers at night and on weekends, with direct coordination with plant personnel and industrial safety supervision, ensuring progress without affecting production. As well as coordination with CFE for interconnection.
Key points
01
Execution at night and weekend hours.
02
Staged planning with constant oversight.
03
Direct communication with plant personnel, safety and hygiene equipment and CFE.
“We were impressed by HHGM's ability to work within an active industrial environment without affecting our operations. Their team was organized, punctual and very professional, achieving a clean and safe installation within the established times.”
Project Manager at Borgwarner