Sujio

Migration of qualified users from ten charging centers across the republic, simultaneously.
Migration of 25 load centers
DC/AC Installed Capacity
Problem

One of the main problems was the simultaneous coordination with the different offices distributed throughout the country, each with different electrical configurations and operating conditions. This required careful planning and constant communication with local managers, to ensure an orderly and uninterrupted transition in the company's continuous operation.

Simultaneous coordination with multiple offices at the national level.
Diversity of electrical configurations and operating conditions.
Careful planning to adapt the implementation at each site.
Constant communication with local managers to ensure an orderly and seamless transition.

Initial Challenges

The main challenge was to migrate ten cargo centers to private supply, located in different regions of the country, for a company with continuous operation in three shifts. The simultaneous coordination of technical, regulatory and logistical management was key to ensuring the seamless transition in production, ensuring an efficient and safe change towards a more competitive and sustainable energy model.

01

Migration to private supply

The main challenge was to migrate ten cargo centers to private supply in different regions of the country.

02

Continuous operation in three shifts

The company operated around the clock, which required a carefully planned execution.

03

Technical, regulatory and logistical coordination

It was key to simultaneously manage technical, regulatory and logistical aspects to ensure an orderly transition.

04

Efficient and secure transition

The change was made without interruption in production, moving towards a more competitive and sustainable energy model.

Project Timeline

Visual summary of the stages of the project, showing the planning, execution and key times for its proper development.
Mar-21
Kick-off
N/A
Design and Engineering
N/A
Execution & Procedures
Nov-23
Start of operations
Solution
Regional technical teams were formed, supported by centralized oversight and a staggered execution plan, allowing each migration to be adapted to its particularities without affecting the company's continuous operation.
Key points
01
Regional technical teams with unified oversight.
02
Migration plan adapted to each electrical configuration.
03
Transition without affecting continued operation.
“What we valued most about HHGM was its ability to coordinate and respond in multiple locations. They maintained clear and efficient communication throughout the process, achieving a seamless migration in our operation.”
Project Manager at Sujio