Saucillo

Construction and connection of more than 50km of overhead and underground medium voltage line for an industrial park
50 km of medium voltage hybrid line
DC/AC Installed Capacity
Problem

One of the main problems was the complexity of the combined route of the overhead and underground lines, which involved crossing roads and coordinating permits with different local agencies and with CFE. This required precise technical and administrative management, ensuring the correct interconnection of the system without affecting park operations.

Complexity of the combined overhead and underground line layout.
Precise technical and administrative management together with CFE.
Crossing roads and coordinating permits with local agencies.
Secure system interconnection without affecting park operations.

Initial Challenges

In this project, the main challenge was to design and execute the medium voltage line, combining aerial and underground sections, to achieve the interconnection of the industrial park with the local CFE substation. Detailed planning and close coordination with the authorities and the commission were required, ensuring regulatory compliance, operational safety and timely commissioning.

01

Design of the medium voltage line

The main challenge was to design and execute a medium voltage line that would combine aerial and underground sections.

02

Interconnection with CFE substation

The infrastructure was developed to connect the industrial park with the local CFE substation efficiently.

03

Institutional planning and coordination

Detailed planning and close coordination was carried out with local authorities and CFE.

04

Compliance, Security and Commissioning

The project ensured regulatory compliance, operational safety and entry into operation in a timely manner.

Project Timeline

Visual summary of the stages of the project, showing the planning, execution and key times for its proper development.
Jul-19
Kick-off
N/A
Design and Engineering
N/A
Execution & Procedures
Sep-22
Start of operations
Solution
A comprehensive technical design was developed with optimized routes and prior coordination with CFE and local authorities, which allowed the work to be carried out safely, complying with regulations and avoiding delays in the final interconnection.
Key points
01
Comprehensive design with optimized routes.
02
Coordination with CFE and local authorities.
03
Regulatory compliance and implementation without delays.
“HHGM managed a complex project with great technical expertise and excellent management before CFE and local authorities. His team showed commitment, order and transparency, ensuring smooth interconnection.”
Project Manager in Saucillo

Liberate you potential and request your quote.

A strategic improvement for your entire operation.
Our team analyzes your current infrastructure, identifies hidden inefficiencies and designs a customized solution that reduces energy costs, improves system performance and strengthens long-term operational stability.