BorgWarner

The project was developed for a company in the automotive industry, which had a high energy consumption and required the decarbonization of its production chain.
942.5
Annual Energy Generated
Problem

The limitation of schedules for carrying out installation work, since the production areas were kept operating continuously. This made it necessary to carefully coordinate access, maneuvers and safety measures such as working at heights and work with electrical hazards, as well as carrying out part of the tasks so as not to interfere with the production line, coordinating with CFE.

Schedule restriction due to continuous operation of the plant.
Complex accesses and maneuvers within productive areas.
Risks associated with working at height and electrical work
Coordinated interconnection with CFE.

Initial Challenges

Technical and logistical coordination within the automotive company's facilities, where it was necessary to carefully plan the installation of the panels between the company and the CFE. In addition, structural and electrical adjustments were made to ensure the compatibility of the solar system with existing infrastructure, ensuring an orderly and safe development of the project.

01

Technical coordination with CFE

Joint planning for a safe and orderly interconnection.

02

Infrastructure adjustments

Structural and electrical adjustments for system compatibility

03

Secure system installation

Controlled execution with high safety standards.

Project Timeline

Visual summary of the stages of the project, showing the planning, execution and key times for its proper development.
Sep-23
Kick-off
Oct-23
Design and Engineering
Nov-23
Execution & Procedures
Feb-24
Start of operations
Solution
A work plan was drawn up in stages, carrying out critical maneuvers at night and on weekends, with direct coordination with plant personnel and industrial safety supervision, ensuring progress without affecting production. As well as coordination with CFE for interconnection.
Key points
01
Execution at night and weekend hours to minimize impacts on the operation.
02
Staged planning with constant supervision throughout the process.
03
Direct and coordinated communication with plant personnel, safety and hygiene equipment, and CFE.
Project results
17%
Savings%
493 tons CO2
CO emissions2
18,978
Planted Trees
“We were impressed by HHGM's ability to work within an active industrial environment without affecting our operations. Their team was organized, punctual and very professional, achieving a clean and safe installation within the established times.”
Project Manager at BorgWarner